Krong No 3 hydropower plant inaugurated in Lam Dong

Monday, 04/04/2016 09:39
The Trung Nam Hydroelectric Corp on April 2nd inaugurated the Krong No 3 hydropower plant in Da Tong commune, Dam Rong district, Lam Dong province.

Krong No 3 hydropower plant inaugurated in Lam Dong (Photo: VNA)

Located on a branch of the Dak Rrong No River, the plant has a total investment of VND685 billion (US30.7 million) with a capacity of 18 MW.

It is designed to provide 63.51 million kWh of energy a year, contributing to ensuring the power supply to Lam Dong and Dak Lak province.

The new facility is part of the Krong No hydropower project and includes two hydropower plants: Krong No 2 and Krong No 3. The Krong No 2 plant is scheduled to be put into operation this year.

The Krong No hydropower project has a combined capacity of 48 MW, with a total investment of VND1,850 billion (USD83 million). When fully operational, it is expected to provide 176 million kWh of energy a year.

Also in Da Tong commune, the Trung Nam Krong No Corp held a ground-breaking ceremony for the Dak Kgui hydropower the same day.

With a total investment of VND119 billion (USD5.3 million), the plant will supply a total of 14.28 million kWh once completed after 15 months of construction./.

CPV/NDO