Hoa Xuan transformer station serving APEC put into operation (Photo: PANO)
The construction was inaugurated in September 10th, 2016, with investment capital of over VND86 billion.

So far, to ensure stable power supply for APEC, the Da Nang city Power Company put into operation the 110kV Hoa Lien transformer station, increased the capacity of the An Don and Xuan Ha transformer stations, and upgraded the 22kV electricity supply for Ba Na tourism area.

In the future, the company will complete key power supply constructions serving APEC./.