Main contractors are speeding up the road construction which connects Hai Ha sea port industrial park and National Highway 18A in order to attract more investors to the park.
The 52 - meter- wide road has a length of over 6 kilometers. It is a type 1 urban road with 6 lanes. Main contractors are Cuong Thinh Construction Investment Group and Thanh Trung Construction and Trading Co., Ltd.
With a total capital investment of VND533 billion from the central budget, project completion is expected within 70 months. Currently, thanks to favorable weather conditions, contractors are deploying mechanics and workers and have increased working shifts to achieve the target date.
So far, some 60% of the road’s ballast has reached completion. Once operational, the road will actively help Quang Ninh province in general and Hai Ha district in particular, speeding up the overall socio-economic development master plan./.