Da Nang increases power capacity to serve APEC

Wednesday, 28/06/2017 14:48
The Da Nang Power One-member Limited Liability Company has successfully completed the commissioning and put into operation the T2- 63 MVA transformer in 110kV Lien Tri substation.



Completing the increase of capacity of 110kV Lien Tri substation. (Photo: laodong.com.vn)

At the same time, the company also increased the capacity of the substation to ensure power for the city’s central areas and events of APEC 2017 in Da Nang in November 2017.

Located in Hoa Thuan Dong precinct, Hai Chau district, the 110kV Lien Tri substation is  one of the key projects of the city’s grid.

So far, the company has completed most of its 110kV projects to serve APEC 2017.

Currently, only 110kV Ngu Hanh Son substation is under urgent construction and is expected to be completed by July 31st./.